Permanent Radioactive Material Storage

Design & Build Project

Permanent NDT Bunker for Industrial Gamma Radiography

RADXION was engaged to design and deliver a permanent, purpose-built Non-Destructive Testing (NDT) bunker for industrial gamma radiography. The facility is intended for continuous, high-throughput inspection operations, ensuring maximal shielding performance, ergonomic workflow, and full regulatory compliance.

Co-60 up to 3.7 TBq0.8 m Concrete Walls & Roof≤ 0.02 mSv/h External10-Month Delivery

02

Objectives

Long-Term Facility

Deliver a robust, long-term facility with minimal maintenance.

Shielding Performance

Provide shielding to reduce external dose rates to ≤ 0.02 mSv/h under worst-case source operations.

Ergonomic Workflow

Integrate ergonomic features to streamline radiographer movements and equipment handling.

Advanced Safety Systems

Incorporate advanced safety, monitoring, and emergency-response systems.

03

Scope of Work

  1. Site analysis and geotechnical survey for foundation design.
  2. Detailed architectural and structural engineering.
  3. Shielding calculations for multiple radionuclide sources (up to Co-60).
  4. Full mechanical, electrical, and control systems design.
  5. Factory fabrication of modular shielding panels and on-site assembly.
  6. Commissioning, acceptance testing, and staff training.

04

Site & Structural Design

Foundation

Reinforced concrete slab on compacted aggregate base, designed for local soil conditions.

Walls & Roof

0.8 m thick reinforced concrete (density ≥ 2.5 g/cm³), with integrated steel rebar and external waterproofing membrane.

Flooring

Wear-resistant epoxy finish, chemical- and radiation-tolerant.

Access Points

Lead-lined personnel door with labyrinth seal, and a motorized load-door for equipment transfer.

05

Shielding Engineering

Primary Barrier

Minimum 0.8 m concrete equivalent (≥ 10⁷ attenuation at 1.25 MeV).

Secondary Barrier

20 mm lead-equivalent removable panels for maintenance access.

Penetration Design

Custom labyrinth chases for cables and utilities; no direct line-of-sight paths.

Dose-Rate Compliance

Modeled and validated so that under continuous Co-60 operation (3.7 TBq), external dose rates remain ≤ 0.02 mSv/h.

06

Mechanical & HVAC Systems

Ventilation

10 air-changes per hour via HEPA-filtered supply and exhaust.

Temperature Control

HVAC unit maintaining 18–24 °C for optimal equipment and operator comfort.

Heat Removal

Dedicated fan-coil unit on source storage alcove to dissipate decay heat.

07

Electrical & Control Systems

Power Distribution

Redundant feeds with UPS backup for critical loads (interlocks, alarms, lighting).

Interlock Logic

PLC-based control interlock, with force-off on door-open or over-temperature.

Monitoring

Networked radiation monitors (gamma and neutron), differential pressure sensors, and environmental logging.

Human-Machine Interface

Touchscreen panel at entry vestibule; remote monitoring console in control room.

08

Ergonomics & Workflow

Source Alcove

Reference-positioned cassette port with adjustable fixture height.

Equipment Storage

Integrated shielded lockers for sources, film cassettes, and tools.

Operator Path

Clearly delineated safe pathways marked with photoluminescent tape.

Control Room

Glass-reinforced polycarbonate viewing window with shutter and audio intercom.

09

Safety & Emergency Provisions

Alarms & Indicators

Visual warning strobes and sirens interlocked to source drive.

Fire Protection

Inert-gas fire-suppression system in source storage alcove.

Emergency Egress

Two means of exit; illuminated exit signs on battery backup.

Drills & Procedures

Provision of emergency-response plan and annual full evacuation drills.

10

Materials & Procurement

Concrete High-density mix with iron-oxide aggregate (≥ 2.5 g/cm³).
Shielding Panels Factory-cast lead modules in stainless-steel trays.
Structural Steel S355 marine-grade for door frames and support lintels.
Finishes & Sealants Radiation-tolerant epoxy coatings; silicone gaskets rated for –40 °C to +150 °C.

11

Regulatory Compliance

IAEA SSR-6 for Category I sources and Type B(U) packages.
Local building code approvals for industrial radiation facilities.
ISO 11625 interlock and alarm performance standards.
FANR (UAE) licensing for fixed radiographic installations.

12

Deliverables & Timeline

Deliverable
M1M2M3M4M5M6M7M8M9M10
Design PackageCivil, mechanical, electrical drawings and shielding report.
Month 1–3
Fabrication & DeliveryShielding modules and mechanical skids.
Month 4–6
Site Works & AssemblyCivil works and installation.
Month 7–9
Commissioning & HandoverAcceptance testing, documentation, and training.
M10

Conclusion

RADXION’s permanent NDT bunker design delivers a high-performance, future-proof facility that maximizes operator safety, regulatory compliance, and operational efficiency for all routine and high-throughput industrial radiography tasks.